Building Refresh for Freshers

Building Refresh for Freshers

Leeds University Union

This summer, we’re working hard to improve our building just in time for freshers, and we’re excited to let you know our plans to make the building even more accessible, get the most our the space outside the precinct, upgrade Terrace’s legendary terrace and improve the south entrance to the building.

 

South Entrance Project

This project will start on Saturday 28 July and should take 2-3 weeks to finish. You'll be able to get into the building via the main entrance during this time.

Accessibility

We'll be starting our new accessibility works with upgrades to the doors from the main foyer. These works will start on Tuesday 31 July, and on 30 August the doors will be made accessible.

Terrace

We're revamping the Terrace outdoor area starting this week (more on the brand-spanking new look here), and we'll keep you informed of any closures.

External works to the front of LUU – Landscaping

From Monday 30 July – Friday 7 September we'll be refreshing the North Entrance of the building, including the installation of a new garden/seating area, a new seating deck and a revamped stairwell to the retail areas.

 

Of course, all the improvements will mean some building work, but we'll make it easy for you to still pop in whenever you want.

If you've got any more questions about the building works, you can get in touch with  l.johns@leeds.ac.uk.